Timelines &
Timescales

The following key milestones for the Belfast campus development have been agreed:

Date Key Milestone
Completed Project mobilisation
Completed Issue of Project Brief
Late 2011 Concept design for new campus
Early 2012 Submission of planning application
Early 2012 Completion of detailed design
Late 2012 Approval of planning application
Mid 2013 Appointment of contractor
Early 2018 New campus ready for occupation
Mid 2018 Transition from Jordanstown
Late 2018 New campus operational